Project Profile

Superterminal 1, Hong Kong International Airport , 2007

Name
Alternative proposal for L3 existing computer room expansion at Superterminal 1
Completion
12/2007
Location

Lantau Island, Hong Kong

Client
Hong Kong Air Cargo Terminals Ltd.
Consultant
Parsons Brinckerhoff (Asia) Ltd.
Main Contractor
ATAL Engineering Ltd.
Scope of  Work
Packaged contract for the internal fitting out of L3 existing computer room expansion for Superterminal 1 at Hong Kong International Airport, including builders' works, raised flooring, precision air conditioning and electrical installation.
Description
The air conditioning and electrical installation comprising Low voltage switchboard cubicle / Cable & Wiring system / Floor trunking system / Water Leakage Detection system / Lighting system / Earthing system / 480KVA UPS system / 144 refrigeration tons Canatal Precision Air-conditioning units / 60 HP VRV Air Conditioning Units/ Raised flooring and Waterproof Ceiling.